Modular Kitchen Planning Checklist: From Measurement to Installation

By Delma Design Team Updated 3 min read
Designer measuring a room with a tape while the homeowner takes notes

Quick answer

Plan a modular kitchen in this order: set a budget, finish civil, plumbing and electrical work, get an accurate site measurement, decide your appliances, approve a 3D design and itemised quote, then allow about 35–40 days for manufacturing and installation. Check alignment, hardware and sealing before handover.

Key takeaways

  • ✓Finish civil work, tiling, plumbing and electrical points before the final measurement.
  • ✓Decide every appliance and its size before the design is frozen.
  • ✓Approve the design in 3D with an itemised quote, so there are no surprises.
  • ✓Delma typically needs 35–40 days from final design approval to installation.

A modular kitchen is built in a factory and assembled on site, so good planning before manufacturing is what makes it fit perfectly. Use this checklist whether you are building a new home in Mohali or renovating a kitchen in Chandigarh or Panchkula.

Step 1: Set your budget and priorities

Decide an overall budget, including the countertop and appliances, and keep a small contingency for surprises. Then list your priorities: more storage, an easy-to-clean finish, space for two cooks, or a premium look. Our cost guide gives indicative figures for each budget level.

Step 2: Finish civil, plumbing and electrical work

Modular cabinets are made to millimetre measurements, so the room must be ready first.

  • Complete any wall changes, plastering and floor tiling.
  • Fix the position of the sink, water inlet and drain; plan the water purifier and dishwasher connections.
  • Plan the gas line or electric hob supply.
  • Mark the chimney duct route to an outside wall.
  • Add electrical points for every appliance, plus counter-height sockets for mixers and small appliances.

If you have your own contractor, your designer should give them a drawing with the exact heights and positions of every point.

Step 3: Get an accurate site measurement

A designer should measure the room after civil work, noting wall lengths, ceiling height, beams, columns, windows, doors, switchboards and pipe positions. Small details such as a window sill height or a beam over the hob change the design, so on-site measurement matters.

Designer and installer checking a kitchen island on site

Step 4: Decide your appliances

Freeze your appliance list before the design, with model sizes where possible:

  • chimney and hob (number of burners, width)
  • built-in or freestanding microwave and oven
  • refrigerator (single or double door, width)
  • dishwasher
  • water purifier
  • any coffee machine, air fryer or other counter appliance you use daily

Step 5: Choose layout, materials, finishes and hardware

Work with your designer on the layout (see the layout guide), the carcass material (HDHMR vs plywood), the shutter finish (finishes guide) and the hardware (hardware guide). Compare finish samples next to your countertop in daylight.

Step 6: Approve the 3D design and itemised quote

Before anything is manufactured, you should see a 3D design of your kitchen and a quote that lists each item separately: carcass, shutters, hardware, accessories, countertop, appliances, installation and taxes. Read it carefully and confirm board types, thicknesses and hardware models.

Step 7: Manufacturing

Once you approve the design, the modules are cut on CNC machines, edge-banded and assembled in the factory. At Delma this stage, together with installation, usually takes about 35 to 40 days; solid wood finishes take around 75 days. Use this time to finish painting and any remaining site work.

Step 8: Installation and handover checklist

Installation on site usually takes a few days. Before you sign off, check:

  • shutters are level with even gaps
  • every drawer, hinge and lift-up closes softly
  • all edges are banded and there are no chipped corners
  • the sink, taps and countertop joints are sealed with no leaks
  • appliances fit, are connected and work
  • the chimney duct is sealed at the wall
  • you have the warranty details and care instructions in writing

Ready to start?

Delma handles design, manufacturing and installation, and can guide your contractor on civil and electrical work. Read more about our process and services, or book a free design consultation in Mohali, Chandigarh or Panchkula.

Frequently asked questions

How long does it take to install a modular kitchen?

+

At Delma, manufacturing and installation usually take about 35 to 40 days after you approve the final design. Solid wood finishes take around 75 days. On-site installation itself typically takes a few days once the modules arrive.

Should tiling be done before the modular kitchen?

+

Floor tiling, wall plastering and the main plumbing and electrical work should be completed before the final measurement, so the cabinets fit the finished room. Dado tiles behind the counter can be planned with your designer, since they are often fitted after the countertop.

What electrical points do I need in a modular kitchen?

+

Plan dedicated points for the chimney, hob (if electric), microwave, oven, refrigerator, water purifier, dishwasher and any under-cabinet lighting, plus several sockets at counter height for mixers and small appliances. Your designer should mark their exact heights on a drawing.

What should I check when the kitchen is handed over?

+

Check that shutters are aligned with even gaps, drawers and lift-ups close softly, all edges are banded, the sink and countertop joints are sealed, appliances fit and work, and there is no gap between the countertop and the wall.

Prices and timelines in this guide are indicative for Mohali, Chandigarh, Panchkula and nearby, and depend on your exact measurements, materials and hardware. For a figure for your home, ask for a free itemised estimate.

Free consultation

Get expert advice for your home

Share your details and our designer will call you within 24 hours with ideas and an estimate. No obligation.

  • ✓ Free 3D design of your space
  • ✓ Transparent, itemised estimate
  • ✓ Free site measurement in Mohali, Chandigarh & Panchkula

Prefer to talk now? Call +91 78076 12341

We only use your details to contact you about your project.